Owner
Utilities Kingston
Value
~ $7.1 million
Partner
CH2M HILL
Delivery Model
Municipal & Public Infrastructure
Year
2016
Carried out over two years, the project required boring a 185-metre-long rock tunnel with a diameter of 1.8 metres. We deployed 1,100 metres of 1050-mm forcemain pipe and installed large, poured-in-place valve chambers. As with many of our projects, our infrastructure wastewater management works on James Street met or exceeded Ontario government standards.